Public Utilities

Rwanda
  • 2001 – Valuation of all of the assets of the electricity, water and gas public utility, Electrogaz, comprising of land, buildings, water treatment works and distribution, hydro and thermal power stations and power transmission and distribution and gas extraction equipment and all other plant, machinery and equipment.
Eritrea
  • 2001 – Valuation of all of the assets of the public utility Telecommunications Service of Eritrea (TSE)comprising of the specialised telecommunications equipment and all other buildings, plant, machinery and equipment.
Zimbabwe
  • 1997, 2004 & 2005 and 2008 – Valuation of fixed assets of the Zimbabwe Electricity Supply Authority (ZESA) including housing, generation, transmission and distribution plant and machinery inclusive of civil works and ancillary assets including vehicles, workshops, computers and training equipment for the privatization of Hwange power station, for commercialization purposes and the construction of a new assets register for successive companies created by the Electricity Act. The valuation was initially carried out in conjunction with Nor Consult International AS of Sandvika, Norway and AF-Enegikonsult Sdy AB of Sweden.
Kenya
  • KenGen 2009 – Valuation of fixed assets, including housing, generation, transmission and distribution plant and machinery inclusive of civil works and ancillary assets including vehicles, workshops, computers and training equipment.
Tanzania
  • Tanesco 2010 – Valuation of fixed assets, including housing, generation, transmission and distribution plant and machinery inclusive of civil works and ancillary assets including vehicles, workshops, computers and training equipment.
Malawi
  • Malawi Telecommunications Limited 2006 & 2010 – Valuation of all of the assets of the public utility (MTL) comprising of the specialised telecommunications equipment and all other buildings, plant, machinery and equipment.